Lone Star NGL Cryogenic Plant

Our Task

CCC Group was general contractor for the construction of a 250MM cf/d NGL cryogenic plant project.

Services Involved

  • Civil and Foundations
  • Grounding Grid
  • Structural Steel
  • Equipment setting
  • Piping installation (Rack Piping & Interconnecting Piping)
  • Offsite Fabrication of Piping and Structural Steel
  • Subcontracted Scaffolding, Insulation, and Painting

Client

Allied Equipment

Pettus, TX

Allied Equipment was formed in 1984 to service the oil and gas processing industry. Allied Equipment is most widely known as a leader in the design and manufacturing of modular gas treating and gas processing facilities.