System 2 Conveyor & Mobile Equipment Installation

Project involved complete dismantle of material handling system in Germany and shipment to Colombia. Once the equipment arrived in Colombia, the project involved rebuilding and erecting the complete mining systems in Drummond’s mine in North Central Colombia. This included installing 6 kilometers of 84′ wide conveyors, mobile sizers, and mobile apron feeders to move the overburden to mobile transfer conveyors
and a mobile spreader for spoil distribution.

Scope of work included all electrical and mechanical work for the entire system including mobile and fixed stackers, conveyors, sizers, and apron feeders. CCC Group provided management, on-site supervision and technical expertise for the project.

Drummond Coal

Colombia, South America

RELATED PROJECTS